Discussion and possible action to refurbish the social services building located at 7401 NE 23rd Street for utility storage.
Estimated improvements:
Demolition - $125,000
Roof - $500,000
Fencing - $50,000
Gate Operators - $50,000
Utility Entry Doors - $5,000
Garage Doors - $5,000
Access Controls & Cameras - $50,000
Estimated Total - $785,000