Title:
|
Discussion and possible action regarding Change Order No. 2 on ODOT Project STP-255C (556) CO. Intersection modification at Britton and Luther Road near Jones . This change order is necessary to compensate the contractor for the underrun of clearing and grubbing. The total value for the change order is $12,489.27 (Twelve Thousand Four Hundred Eighty-Nine Dollars and 27/100). The County share will be reflected in the final cost apportionment of the project Requested by Stacey Trumbo, PE, County Engineer.
|