Title:
|
Discussion and possible action regarding Change Order No. 2 on ODOT Project STP-255C (613) CO - Bridge 30. This change order replaces the Revetment Mattress pay item with Filter blanket and Rip Rap. The total value for the change order is $45,299.80 (Forty-Five Thousand Two Hundred Ninety-Nine Dollars and 80/100). The County share will be reflected in the final cost apportionment of the project Requested by Stacey Trumbo, PE, County Engineer.
|