Title:
|
Discussion and possible action regarding Final Quantity Change Order on ODOT Project STP-255C (556) CO the Intersection modification at Britton and Luther Road near Jones . This change order establishes the final quantity for each item on the original contract and for those items added by change order during construction. The total value for the change order is - $70,697.04 (Negative Seventy Thousand Six Hundred Ninety-Seven Dollars and 04/100). The County share will be reflected in the final cost apportionment of the project Requested by Stacey Trumbo, PE, County Engineer.
|